Vancouver, British Columbia, March 9, 2022 (GLOBE NEWSWIRE) — Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) (“Monument” or “Company”) at a mining site in Serinsing Gold Mine, Malaysia. A groundbreaking ceremony (Fig. 1) will be held to announce the return of the prime contractor, Seong Henng Engineering Works Sdn Bhd (“Seong Henng”). Construction of flotation plant.

Cathy Zhai, President and Chief Executive Officer, commented: Our on-site team manages the project and oversees the prime contractor, Son Heng. We are working together to complete the construction of the flotation plant at a high standard, safely, diligently, on time and on budget, in preparation for a test run at the end of June 2022. “

Figure 1: Groundbreaking Ribbon Cut at Serinsing Gold Mine It is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/2093b803-17fa-495e-9167-279f895ed6c6.

Charlie Northfield, General Manager and Project Sponsor of Selinsing Gold Mine, commented: .. Seong Henng is a Malaysia-based local manufacturing company that has historically successfully built and expanded the Selinsing Gold factory. “

Construction of a vacant plant includes project management, project verification, vacant design and engineering, procurement, construction and commissioning. The flotation plant construction project is 50% complete to date.

Detailed engineering design

Mincore Pty Ltd. (“Mincore”) previously completed a detailed engineering design and now completes a 3D model of the new flotation plant for future additions of the BIOX® plant and auxiliary work (Figure 2). ..

Figure 2: Final 3D model of adding sulfide flotation circuit to gold plant serrinsing It is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/af324d08-9757-45c0-8959-aec4cc231596.

Procurement

The flotation cell supply contract was awarded to BGRIMM Machinery and Technology Co Ltd in Beijing, China. The production of the flotation cell was completed, and the factory acceptance test was successfully conducted on January 25th.th-26th, 2022. Packing is in progress and shipping is scheduled to depart Tianjin on March 15.th2022.

Finland’s Metso Outotec Corporation supplies flotation concentrates and water recovery thickeners. Started manufacturing work and parts procurement.The trial is scheduled for April 12thth, 2022 and thickeners will be delivered to the site in May / June 2022. The thickener has a segmented / bolted design that can be quickly assembled after it is received in the field. It doesn’t take long to complete the installation on time.

The flotation concentrate filter press is supplied by McClanahan Corporation (“McClanahan”), Pennsylvania, USA. All equipment parts have been ordered and production is expected to be completed in March 2022. The filter press assembly will be completed on April 7th.thShipped April 12th It will be delivered to the site in May / June 2022.

Other outsourced equipment includes, but is not limited to: A 50% complete slurry pump, shipping is scheduled for May 9th.thIn 2022, the Afromix Agitator will be completed and will arrive in Port Klang, Malaysia on March 28th.th, 2022. Froth flotation blowers and compressors have been ordered, are 30% complete and in progress, and are scheduled for delivery on May 27.th, 2022. A containerized MCC switchroom design, manufacturing, delivery, and test run contract has been signed and is scheduled for delivery on May 13.th, 2022. A purchase order for concentrated samplers and helical rotor reagent pumps has also been issued. Production was in progress for both orders. The production of 11kV / 415V transformers was reported to be 100% complete.

Involvement of major construction contractors

A dedicated project team has been completed and consists of project managers, assistant project managers, lead engineers, senior engineers, electrical engineers, procurement engineers, and workers. The project team oversees the construction work.

Song Heng has been appointed as the prime contractor. They had previously undertaken construction work to build and expand a Selinsing gold processing plant for the past decade. They commissioned a refurbishment of the CITIC ball mill in 2009 as part of a first-stage gravity-only process plant. Then, in 2010, the phase 2 carbon of the leachate circuit was constructed and commissioned. In 2012, we built / commissioned a new CITIC ball mill and three new leachate tanks for Phase 3 plant expansion.Song Heng received a certificate on the start date of January 12thth2022, contract period 6 months, completion date July 7th2022.

R & D work

The completed pilot plant consists of a ball mill and classifier, a coarse / scavenger flotation cell, and a three-stage cleaner flotation. (Fig. 3). A 1 ton sample of transition ore was crushed in a laboratory fine jaw crusher until it passed 100% 2 mm and fed to a pilot plant ball mill. Samples were processed using the same reagent regime planned for a full-scale plant. A total of 50 kg of flotation concentrate was produced and this sample was sent to McClanahan for filter press testing. The antimony leaching test was conducted to support the marketing activities of gold concentrate.

Figure 3: Frothed pilot plant It is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/9e4e3edb-1d0a-4230-8190-25405da06139.

Civil engineering foundation work

Song Heng was mobilized to the scene on January 22ndnd, 2022, started delivery of reinforcing bars (reinforcing bars), reinforcing bar bending devices, formwork, HDPE piping, and fusion splicers. A temporary benchmark has been set for the tie-in of the survey.

Civil engineering foundation work is underway along with the retaining wall extension work. The final excavation was completed, the rebar and formwork were installed, and the first concrete injection was made on February 17th.th, 2022 (Fig. 4). To date, the retaining wall has been extended by 50%. Work in this area will continue in parallel with the foundation of the new reagent mixed building, followed by civil engineering work for concentrates and water recovery thickeners, reagent warehouses and filter press buildings. Structural steel and tank production is underway at the Songchen workshop.

Figure 4: First concrete injection at the flotation foundation It is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/db3adc6e-9ec9-46e8-9e99-3b201080fad4.

Other contractors working at construction sites rewired HV power cables to primary and secondary ball mills, connected power and communication cables to the project office, performed plate bearing tests on the plant footprint, and performed plate bearing tests. We tested the soil resistance of the new transformer. ..

Transition to flotation

Dry commissioning of the new flotation plant and related equipment is scheduled to begin on June 1.st, After 2022. CIL plant will continue to operate until June 30th, 2022.Frothation plant tie-in and wet test runs will begin on July 1ststContinues until July 14, 2022th, 2022. The ore test run is scheduled to begin on July 15.th, 2022. The gold remaining in the circuit is recovered by emptying the leachate and CIL tank slurry, placing the harvested carbon in a bag and later elution. The elution circuit will continue to operate for approximately one month after the CIL plant shuts down.

About monuments

Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) is a Canadian established gold producer who owns and operates the Serinsing Gold Mine in Malaysia and the Murchison Gold Project in the Murchison region of Western Australia. It has a 20% stake in the Tuckanarra Gold Project, which is co-owned with Odyssey Gold Ltd in the region. With approximately 200 employees in both regions, we are committed to the highest standards of environmental management, social responsibility, health and safety for our employees and their neighbors.

Kathy Zai, President and CEO
Monument Mining Limited
Suite 1580 -1100 Melville Street
Vancouver, British Columbia V6E4A6

For more information, please visit the company website at www.monumentmining.com or contact us at:

Richard Cushing, MMY Vancouver T: + 1-604-638-1661 x102 rcushing@monumentmining.com

“Neither the TSX Venture Exchange nor its regulatory service provider (the term is defined in the TSX Venture Exchange Policy) is responsible for the validity or accuracy of this release.”

Description of future prospects

This news release contains a statement containing information about the future outlook for Monument, its business and future plans (“Future Outlook Statement”). Forward-looking statements include non-historical expectations, plans, objectives, or future events, with our plans for mineral projects, and the timing of proposed programs and events mentioned in this news release. A description that includes the result. In general, forward-looking information refers to forward-looking terms such as “plan,” “expect,” “not expect,” “expected,” “budget,” “plan,” and “estimate.” Can be identified using. “Predict”, “intended”, “predict”, “unexpected”, “believe”, or a variation of such a word or phrase, or a particular action, event, or result is “potential” , “Possible”, “Possible”, “Possible” or “Take”, “Occurs” or “Achieved”. Forward-looking statements in this news release are subject to a variety of risks, uncertainties, and other factors, and actual results or outcomes are largely expressed or implied by forward-looking statements. It may be different. These risks and other specific factors include, but are not limited to: Risks associated with general business, economic, competitive, geopolitical and social uncertainty. Uncertainty about the outcome of current exploration activities. Uncertainty in the progress and timing of development activities. Risks of overseas business; Other risks inherent in the mining industry, as well as other risks described in discussions and analysis by our management and technical reports on our projects. All of these are available under our profile at SEDAR at www.sedar.com. Key factors and assumptions used in this news release to create forward-looking statements include: Beyond monumental control; assumptions and expectations regarding the findings of our project. Assumptions about the future price of gold in other minerals. Estimated future production timing and quantity. Expected timing and results of development and exploration activities. Costs of future activities; Capital and operating costs; Successful exploration activities; Mining or processing issues. Forex rates; also assumed to be all factors described in the discussion and analysis by the company’s management, and in the technical report on the company’s projects. All of these are available under the company profile at SEDAR at www.sedar.com. We have attempted to identify key factors whose actual performance may differ materially from those contained in the forward-looking statements, but may cause results to differ from what is expected, estimated or intended. There may be other factors. Actual results and future events may differ materially from those expected in such statements, and there is no guarantee that such statements will be accurate. Therefore, readers should not place undue reliance on forward-looking statements. We do not undertake to update any forward-looking statement except in accordance with applicable securities law...


CBJ News Maker

Monument announces groundbreaking ceremony at Serinsing for buoyancy construction in Malaysia, Canadian Business Journal

Source link Monument announces groundbreaking ceremony at Serinsing for buoyancy construction in Malaysia, Canadian Business Journal

Related Articles

Back to top button