Acciona sues Metro Vancouver for $ 250 million at North Shore plant

The company claims that delays and cost overruns are primarily due to poor sites and flaws designed by Metro Vancouver.

Article content

Spanish construction giant Acciona is suing Metro Vancouver for a $ 250 million recovery for unfairly ending a contract to build a wastewater treatment plant on the North Shore, the company said on Thursday, the highest in British Columbia. Claims to have filed a lawsuit in court.

Advertising 2

Article content

The project has been plagued by the issue of Metro starting to select too small sites to be affected by multiple risks and errors in its own design that requires thousands of changes that would inflate the budget to over $ 1 billion. The company claims in the notice of the claim.

Metro Vancouver very publicly dismissed Acciona from the project last October, and its design and construction contractor was “unfulfilled and consistent, including on-time delivery of the facility, which was two and a half years at the time. I couldn’t fulfill my contractual obligations. ” Behind the schedule.

In January, the provincial district officially terminated its $ 504 million project in 2021 with Acciona and hired a new contractor, PCL Constructor West Coast, to get the construction on track. I made a plan to return to. September.

Advertising 3

Article content

However, the detailed 98-page claim submitted by Acciona was largely due to the design flaws of Metro Vancouver itself and the failure to approve the necessary changes in a timely manner, resulting in numerous delays and cost overruns. Outlines the company version of what was happening behind the scenes.

This allegation has not been proved in court and Metro Vancouver has not submitted a response.

Last fall, when Metro Vancouver said Acciona Wastewater Solutions LP, a subsidiary of Acciona, seemed to abandon the project, the company was “integrity” to solve the project’s problems with a new schedule scheduled to be completed in 2025. I was participating in the discussion. ..

“By mid-2021, it may not be possible to build a North Shore (wastewater treatment plant) at a project site selected by (Metro Vancouver’s larger Vancouver sewage and drainage district) in accordance with the requirements of the project agreement. It became clear, “according to the lawsuit.

Advertising 4

Article content

The company claims that the contract will require significant changes due to “discovery of rampant errors and conflicts” in design and construction specifications that were not expected when the contract was signed in 2017. Insist.

Acciona advised Metro Vancouver that it would not be possible to meet all the requirements of the project contract, but according to the proceedings, the districts demanded that the company meet the delivery date of September 19, 2023, after which ” Insisted on terminating the project contract .. “

According to the claim, “Acciona’s updated project schedule required under (Project Contract) is the exact reality of Acciona’s plan to complete its (contract) obligations at all critical times. Provided a typical expression. “

Advertising 5

Article content

Metro Vancouver’s “termination of (contract) is illegal, and Accciona seeks to recover all losses resulting from such tort,” the company claims.

Metro Vancouver estimates at least $ 250 million in damages, including $ 100 million milestone payments for work pending last fall, $ 50 million secured by Acciona’s design and construction security, and other damages. ..

Come more …


More news, less ads, faster load times: Get unlimited adlite access to Vancouver Sun, Provins, National Post, and 13 other Canadian news sites for $ 14 / month or $ 140 / year. Subscribe now from Vancouver Sun or Province.

    Advertisement 1

Comment Comment

Postmedia maintains a lively yet civic discussion forum and encourages all readers to share their views on our articles. Moderation can take up to an hour for comments to appear on your site. Comments are relevant and should be stored with respect. You have enabled email notifications. You will now receive an email when you receive a reply to a comment, when the comment thread you are following is updated, or when a user follows a comment. For more information and details on how to adjust your email settings, see Community Guidelines.

Acciona sues Metro Vancouver for $ 250 million at North Shore plant

Source link Acciona sues Metro Vancouver for $ 250 million at North Shore plant

Related Articles

Back to top button